Welcome!

Our services include:

DESIGN
DESIGN VERIFICATION
INTEGRITY ASST.
INSPECTION
 
  • Pressure Vessels
  • Pressure Piping
  • Boilers
  • Relief Systems
  • Tanks
  • Heat Exchangers
 
ANALYSIS / TOOLS
 
  • Finite Element (FEA)
  • Stress Analysis
  • Fatigue
  • Creep Rupture
  • Fracture Mechanics
 
 
Please download our Capability Statement - (281k)
 
Recent News
 
11 Nov 10 -- Inspection and Integrity Assessment of a Dent in a Tank Combined to Recommend Continued Safe Storage of Dangerous Solvent [Show|Hide]
 
KJ Beer did an inspection of a second hand storage tank used to store a dangerous industrial solvent for Profill in Wangara. The tank had incomplete design documentation which KJ Beer’s AICIP recognised inspector determined. The inspector identified a significant dent in the shell of the horizontal tank near the saddle support. The inspector measured the deformation due to the dent and found it to be greater than the allowable in API 650. The deformation due to the dent was referred to the office for a more detailed assessment in accordance with API 579 Level 2. This assessment proved that the tank was not fit for continued service. It was recommended that the tank be replaced. By combining inspection and an office based integrity assessment service KJ Beer provided Profill with a recommendation to ensure continued safe storage of a dangerous solvent in 2 working days.
9 Nov 10 -- Challenging Design Verification of Air Receivers with Imported 'Freefall' Amusement Ride [Show|Hide]
 
  KJ Beer were requested to verify the design of two vertical air receivers which are part of the air drying equipment for the recently imported 'Freefall' amusement ride at Adventure World. The vessels had incomplete design documentation. An inspection was performed to determine the missing design information required for the design verification. It was recommended that non-destructive testing (NDT) be performed on the vessel welds to prove their soundness. Several non acceptable weld defects were discovered and a weld repair procedure was prepared. The vessels were successfully repaired, tested and registered with WorkSafe WA.

There were another three air receivers located on the recently imported 'Freefall' amusement ride at Adventure World requiring design verification which also had incomplete documentation. One of the receivers was located halfway up the 'Freefall' tower making it difficult to get to, but this didn’t stop KJ Beer’s AICIP inspector getting the missing design information. The recommended NDT on the vessel welds revealed non acceptable weld defects in two vessels. Adventure World requested KJ Beer design two replacement vessels.

Having engineers with AICIP competency was vital to KJ Beer finishing this challenging job.
6 Oct 10 -- In-situ Post-Weld Heat Treatment for BP Refinery Depropaniser [Show|Hide]
 
A 30 m tall Depropaniser pressure vessel located at BP’s Kwinana refinery was shutdown and inspection showed defects in a nozzle located approximately half way up. An in-situ repair was proposed to re-weld the nozzle followed by a post weld heat treatment (PWHT) of a full circumferential 1 metre wide band of the shell which included a manway. KJ Beer was contracted to determine whether the reduction of the yield strength in the shell at PWHT temperature (650°C) would compromise the structural integrity of the vessel during the PWHT holding time.

Rigorous mathematical analysis was carried out, which involved assessment of general and localised stresses in the shell due to temperature gradient, vessel weight and wind. KJ Beer engineers worked through the weekend to meet BP’s required completion.
The results indicated that the structural integrity of the vessel was not compromised and it was safe for BP to complete the in-situ repairs and PWHT. (Click on far-left thumbnail to enlarge image)
14 Apr 10 -- A-Frame Gantry Crane Design [Show|Hide]
 
KJ Beer was recently commisioned to assess the mechanical integrity of an A-frame gantry crane which was subjected to a 2t load, allowed to traverse the top lifting beam. The entire frame was modelled in Caear II and a total of 4 load cases were analysed, including weld and bolt stresses.

Caesar II model:
 
 
15 Feb 10 -- Integrity Assessment of FMC Pump Skid Base [Show|Hide]
 
The team at KJ Beer has just completed an integrity assessment of an FMC pump assembly including 2 pulsation control devices, gear box and motor. The entire skid base was modelled using Caesar II's structural module, which was then analysed using 38 different load cases comprising dead weight, seismic and storm wind loads.

Caesar II model:
 
 
6 Oct 09 -- Australia's World Land Speed challenge [Show|Hide]
 
KJ Beer has been approached by Rosco McGlashan and his team to design the two propellant tanks that will fuel Aussie Invader 5R’s hypergolic rocket engines.

We have been commissioned to design a carbon steel fuel tank capable of holding approximately 320 kg of kerosene bio-fuel and a stainless steel oxidizer tank with a capacity to contain approximately 2500 kg of High Test Peroxide (HTP). Each tank is to be rated for 500 psi of internal pressure.

We are excited to be part of this project and wishes to thank Rosco for the opportunity.
1 Aug 09 -- Proof Engineering Study - Pluto Supply Base Fuels Project [Show|Hide]
20 Jul 09 -- Post Weld Heat Treatment Error Saved by Fracture Mechanics Assessment [Show|Hide]
1 Jul 09 -- Heat Exchanger and Pressure Vessel Design for Worsley Alumina Expansion Project [Show|Hide]
12 Mar 09 -- Tank Mechanical Integrity and Design Modifications in Accordance with API 650-2007 [Show|Hide]
22 Dec 08 -- Power Piping Integrity Assessment [Show|Hide]
21 Jul 08 -- WA Pressure Vessel Expertise Reaches Record Heights [Show|Hide]